ITS Franklin Data Center Spine Switch Upgrades
Scheduled Maintenance Report for UNC Chapel Hill - ITS
Completed
The scheduled maintenance has been completed.
Posted Jun 30, 2021 - 07:00 EDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jun 30, 2021 - 05:00 EDT
Scheduled
The ITS Franklin Data Center spine switches will be upgraded with new firmware to fix some significant and impactful bugs. We expect NO downtime during the upgrade, but some impact is possible. As these switches are redundant to one another, our process is to move traffic over to the switch that is not being upgraded first, isolate the secondary switch and perform the upgrade, then once the upgrade is complete we can then switch the traffic over and do the reverse.
Posted Jun 16, 2021 - 09:52 EDT
This scheduled maintenance affected: Network (Data Center ITS).